Santa Cruz Nutritional Electrical System Documentation
- Perform a comprehensive site investigation to all electrical power panels, MCC, switchboards.
- Record electrical equipment location, size, upstream equipment, condition.
- Make recommendations on equipment replacement.
- Generate a updated one-line diagram.
- Generate an electrical maintenance schedule
EV Chargers Concord
- Installation of new meter socket in existing 800A 480Y/277V switchboard.
- Rooftop conduit from existing 480Y/277V switchboard to new transformer.
- Installation of new transformer and disconnect switch.
- Rooftop conduit from new transformer to new 208V panelboard.
- Installation of new 208V panelboard.
- Trenching of underground conduit across parking lot from new 208V panelboard to EV charging stations.
- Installation of (2) level 2 EV fleet chargers.
- Installation of new 480V panelboard.
- Trenching of underground conduit across parking lot from new 480V panel to pullbox.
- Installation of new conductors in existing conduit from pullbox at end of conduit trench to pullbox adjacent to gate for additional parking.
- Installation of (1) EV fast charger.
RS5 Sidewalk Lighting
Provide engineering design for lighting two cross walks from the main entrance of the office building to the roadway sidewalk.